German Federal Court 2026: Payment Is Due Without Invoice Approval

On 25 February 2026 the German Federal Court of Justice confirmed that a contract clause making the payment period start only once the architect has approved the invoice is invalid. Payment falls due with acceptance of the work and a verifiable final invoice. What that means for trade businesses with unpaid invoices, including deadlines, 2026 default interest and a six-step approach.

Key takeaways

  • Federal Court of Justice (BGH), order of 25 February 2026, case VII ZR 146/24: the client's complaint against the denial of leave to appeal was rejected, so the judgment of the Higher Regional Court of Schleswig of 21 August 2024 (case 12 U 29/23) is final.
  • The clause under which the payment period for interim and final invoices starts only once the architect has approved them is invalid as a standard business term (Section 307 BGB). The client has to accept responsibility for the conduct of their architect (Section 278 BGB).
  • In a BGB construction contract the due date follows Section 650g (4) BGB: acceptance plus a verifiable final invoice. If the client does not raise substantiated objections to verifiability within 30 days, the invoice counts as verifiable.
  • For trades businesses that means: "the invoice has not been approved on our side yet" is not a reason to withhold payment. A commercial customer is automatically in default 30 days after the due date and receipt of the invoice (Section 286 (3) BGB), and the statutory default interest rate has stood at 10.52 percent since 1 July 2026.

A trades business whose work has been accepted and which has issued a verifiable final invoice does not have to wait until the customer's architect, site manager or accounting department has "approved" the invoice. That is what the German Federal Court of Justice settled on 25 February 2026 with its order VII ZR 146/24: a contract clause under which the payment period for interim and final invoices starts only once the architect has approved them is invalid. Payment for the work falls due with acceptance, and 30 days after the due date and receipt of the invoice a commercial client is in default, without any reminder. The excuse "the invoice is still with the architect" therefore moves neither the due date nor default, it costs the customer interest.

What the Federal Court of Justice decided

The case comes from Schleswig-Holstein. In October 2018 a client commissioned a general contractor to build a turnkey house, under a BGB construction contract, not under the VOB/B. The contract had been drafted by the client's architect, negotiated with the contractor and presented for signature. Among other things it stated that the payment period for interim and final invoices starts only once the architect has approved the invoice, and that the contractor has to provide a warranty bond.

After acceptance, which was documented in a protocol, the client did not pay the final invoice. His reasoning: the invoice had not been approved, and the bond was missing. On 21 August 2024 the Higher Regional Court of Schleswig found for the contractor (case 12 U 29/23). On 25 February 2026 the Federal Court of Justice rejected the client's complaint against the denial of leave to appeal (case VII ZR 146/24), which makes the judgment final.

An invoice that has not been approved must be paid too!

IBR 2026, headline of the case note on OLG Schleswig 12 U 29/23, translated from German

The same proceedings turned on a second question that matters for trades businesses as well: the client wanted to set off a contractual penalty for missing deadlines. The court rejected that too, because continuing disruptions had overturned the entire schedule and the contractual penalty had thereby lost its basis.

Why the approval clause is invalid

The court took three steps that carry over to many contracts in the trades.

  1. The clause is a standard business term of the client (Section 305 BGB)

    The contract was provided by the client's architect and presented to the contractor. That makes the clauses ones imposed by the client, and they are subject to review of standard business terms, even though the client did not use a form of his own.
  2. The client has to accept responsibility for the architect (Section 278 BGB)

    Where the architect negotiates and concludes the construction contracts with the knowledge and intention of the client, he is the client's agent for that purpose. The client cannot fall back on the argument that it was the architect who drafted the clauses in his favour. As an aside: drafting contracts is a legal service that an architect is as a rule not permitted to provide under Section 3 of the Legal Services Act, with the corresponding liability risk.
  3. The clause unreasonably disadvantages the contractor (Section 307 BGB)

    It makes the due date depend on an act that lies solely in the hands of the client and his representative. The contractor can neither enforce nor speed up the approval. The clause therefore departs from the statutory model, which ties the due date to acceptance and a verifiable invoice, to the contractor's detriment.

The right of retention based on the missing warranty bond failed for the same reason: that clause too was invalid as a standard business term. So the statutory due date applied.

When payment for work falls due under the law

The benchmark against which the clause failed is set out in Section 650g (4) BGB, the rule on due dates in construction contracts:

The remuneration is to be paid if 1. the customer has accepted the work or acceptance is dispensable under Section 641 (2) and 2. the contractor has issued the customer with a verifiable final invoice. The final invoice is verifiable if it contains a clear list of the services rendered and is comprehensible for the customer. It counts as verifiable if the customer has not raised substantiated objections to its verifiability within 30 days of receipt.

Section 650g (4) BGB, translated from German

The third sentence is the most important one for trades businesses: anyone who spends 30 days without raising substantiated objections to verifiability cannot later argue that the invoice was not verifiable. A blanket "not approved yet" is not a substantiated objection. In the Schleswig case the client had put forward nothing substantial against verifiability within the 30 days, so the invoice was due.

Due date and default for tradesmen's invoices by type of contract
Type of contractFalls dueDefaultLegal basis
Contract for work without construction character (e.g. repair, maintenance, installation)On acceptanceAt the latest 30 days after the due date and receipt of the invoice, without a reminderSection 641 (1), Section 286 (3) BGB
Construction contract under the BGB (construction, restoration, removal or rebuilding of a structure or of substantial parts of it)Acceptance plus a verifiable final invoice; without substantiated objections within 30 days it counts as verifiableAt the latest 30 days after the due date and receipt of the invoice, without a reminderSection 650a, Section 650g (4), Section 286 (3) BGB
Construction contract with the VOB/BPromptly after checking and determination, at the latest 30 days after receipt of the verifiable final invoice; 60 days only by express agreement that is objectively justifiedAfter the due date; the contractor can set a grace period, from the end of which default interest runs, unless default has already occurred earlierSection 16 (3) no. 1, Section 16 (5) no. 3 VOB/B

The 30-day rule of Section 286 (3) BGB applies towards consumers only if the invoice expressly points out this consequence. VOB/B as per the 2016 version.

What default costs the customer in 2026

Default starts the clock on default interest, and that has gone up in 2026. The Deutsche Bundesbank raised the base rate under Section 247 BGB to 1.52 percent as of 1 July 2026, up from 1.27 percent in the first half of the year.

Default interest since 1 July 2026

Base rate, Section 247 BGB
1.52 percent (since 1 July 2026, previously 1.27 percent)
Customer is a business
10.52 percent per year (base rate plus 9 percentage points, Section 288 (2) BGB) plus a flat fee of €40 (Section 288 (5) BGB)
Customer is a consumer
6.52 percent per year (base rate plus 5 percentage points, Section 288 (1) BGB)
Default without a reminder
30 days after the due date and receipt of the invoice (Section 286 (3) BGB); towards consumers only where the invoice says so

On an unpaid tradesman's invoice of €15,000 towards a commercial customer that comes to roughly €131 in interest per month, plus the flat fee of €40. Whoever does not calculate the interest is giving it away.

What trades businesses should do now

The decision only helps those who can cleanly document that the conditions for the due date are met. Six steps that any business can implement:

  1. Document acceptance

    An acceptance protocol with a date and a signature is the strongest evidence. If the customer refuses acceptance without naming a defect, Section 640 (2) BGB helps: set a deadline for acceptance, and if it passes without a notice of defects the work counts as accepted (consumers have to be informed of that consequence in text form).
  2. Make the final invoice verifiable

    Items as in the quotation or the bill of quantities, quantities, unit prices, hours with hourly rates, interim payments deducted, variations shown separately. Record receipt: date of dispatch, ideally with proof for post or email.
  3. Keep an eye on the 30-day clock

    Two periods run in parallel from receipt of the invoice: 30 days for substantiated objections by the customer to verifiability (Section 650g (4) BGB) and 30 days until default (Section 286 (3) BGB). For consumers, put the notice about default on the invoice.
  4. Answer "not approved" in writing

    Short and factual: date of acceptance, date of the invoice, a note that internal approval is not a condition for the payment falling due under BGH VII ZR 146/24, a payment deadline of ten days for example. From then on, state the default interest.
  5. Review your own contracts

    Clauses that tie the due date to an approval, a check or a confirmation by the client are open to challenge under this case law where the client imposes them. Anyone who finds them in contracts from developers, architects or general contractors should not accept them tacitly but have them deleted, or at least know that they are not bound by them.
  6. Define the escalation

    Payment reminder, formal reminder, court dunning procedure or action. A reminder is not legally required, but it is often the quickest route. Anyone who does not want to carry the effort themselves can hand the claim to a debt collection service.

When the customer still does not pay

For small businesses, instructing their own lawyer rarely pays off on claims in the three to five figure range, and their own time is needed elsewhere than for chasing payments. Success-based debt collection services close that gap. One example is ForderFix (German-language site), an offering for trades businesses: upload the unpaid invoice and the last email to the customer, the claim is assigned, and what follows is a legally sound reminder including default interest and, where needed, a court dunning order and an action through a partner law firm. The principle is "no success, no cost": if the claim turns out to be unrecoverable, the business incurs no costs, and where it succeeds a success fee may apply. What matters with any provider: it is not a law firm and does not replace legal advice, and legal representation runs through partner firms.

Whether debt collection, a dunning procedure or your own lawyer: the basis is the same in every case. Prove acceptance, issue a verifiable invoice, 30 days. Since 25 February 2026 that comes with the certainty that a "not approved yet" changes none of it.

Sources

  1. Handwerksblatt: no invoice approval, no money? (BGH VII ZR 146/24, OLG Schleswig 12 U 29/23), in German handwerksblatt.de
  2. ARGE Baurecht at the German Bar Association: case note "No invoice approval, no due date?", in German arge-baurecht.com
  3. dejure.org: OLG Schleswig, judgment of 21 August 2024, 12 U 29/23 (with reference to BGH VII ZR 146/24), in German dejure.org
  4. Section 650g BGB: determination of condition where acceptance is refused, final invoice (gesetze-im-internet.de) gesetze-im-internet.de
  5. Section 286 BGB: default of the obligor (gesetze-im-internet.de) gesetze-im-internet.de
  6. Section 288 BGB: default interest and other damage caused by default (gesetze-im-internet.de) gesetze-im-internet.de
  7. Deutsche Bundesbank: base rate under Section 247 BGB (1.52 percent since 1 July 2026) bundesbank.de

Frequently asked questions

No. Internal approval by the client's architect, site manager or accounting department is not a precondition for the payment falling due. In its order of 25 February 2026 (VII ZR 146/24) the Federal Court of Justice confirmed the judgment of the Higher Regional Court of Schleswig, under which a clause tying the payment period to invoice approval by the architect is invalid as a standard business term. Payment falls due with acceptance of the work and, in a construction contract, with a verifiable final invoice.

Under a simple contract for work, a repair for example, the remuneration falls due with acceptance of the work (Section 641 (1) BGB). Under a construction contract within the meaning of Section 650a BGB, a verifiable final invoice is added (Section 650g (4) BGB). An invoice is verifiable if it sets out the services rendered clearly and is comprehensible for the customer. If the client does not raise substantiated objections to verifiability within 30 days of receipt, it counts as verifiable. A reminder is not needed for the payment to fall due.

The case decided concerned a BGB construction contract from 2018. In VOB/B contracts, Section 16 (3) no. 1 VOB/B governs the final payment: it falls due promptly after checking and determination, at the latest 30 days after receipt of the verifiable final invoice, extendable to 60 days only by express agreement that is objectively justified. There too the due date depends on the verifiability of the invoice, not on an internal approval by the client. The court's reasoning, that the client may not make the due date depend on an act that lies solely in their own hands, argues against such clauses in VOB contracts as well; there is no express decision on that point yet.

Under Section 650g (4) sentence 2 BGB, the final invoice is verifiable if it contains a clear list of the services rendered and is comprehensible for the customer. In practice that means: items matching the quotation or the bill of quantities, quantities and unit prices, for work on a time basis the hours and hourly rates, interim payments deducted, variations shown separately. If the client raises no substantiated objections to verifiability within 30 days of receipt, the invoice counts as verifiable even where it has gaps.

The base rate under Section 247 BGB has stood at 1.52 percent since 1 July 2026 (Deutsche Bundesbank). Under Section 288 BGB that yields default interest of 10.52 percent per year where the customer is not a consumer (base rate plus 9 percentage points) and of 6.52 percent towards consumers (base rate plus 5 percentage points). Towards businesses a flat fee of €40 under Section 288 (5) BGB is added. The base rate is adjusted on 1 January and 1 July each year.

No. Towards a commercial customer, default occurs by itself at the latest 30 days after the due date and receipt of the invoice under Section 286 (3) BGB; a reminder is not required for that. Towards consumers the 30-day rule applies only if the invoice expressly points out this consequence, otherwise a reminder is needed. A payment reminder is still often worthwhile, because it settles many cases without proceedings. A debt collection service can, however, be instructed without a prior reminder.